Written answer by Ministry of National Development on how many HDB flats under SERS are expected to be vacated and whether these vacated flats will be added to the interim housing supply under the PPHS

Feb 26, 2024


Question No: 5497

Question by: Ms Hazel Poa

To ask the Minister for National Development (a) in 2024, how many HDB flats under the Selective En Bloc Redevelopment Scheme are expected to be vacated upon the completion of replacement flats; and (b) whether these vacated flats will be added to the interim housing supply under the Parenthood Provisional Housing Scheme.

Answer:

          In 2024, a total of 992 flats are expected to be fully vacated to facilitate redevelopment under the Selective En Bloc Redevelopment Scheme. There are no plans to use the flats in this site for the Parenthood Provisional Housing Scheme because the site is required for near-term redevelopment.