Written Answer by Ministry of National Development on alternative plans for preserving Ellison Building
Sep 11, 2017
Mr Kok Heng Leun: To ask the Minister for National Development whether he can provide an update on the alternative plans of preserving of Ellison Building in light of the construction of the North-South Expressway.
Answer:
The Land Transport Authority’s (LTA) engineers and conservation specialists have been studying various options to minimise the impact on the affected corner shophouse unit during the construction of the North-South Corridor (NSC). This is still ongoing, as there is a need to weigh the risks to both Ellison Building and the NSC carefully in order to come to a good decision.
The Urban Redevelopment Authority (URA) and LTA will engage heritage groups again, before the final decision is taken.